– Vi er i mål til rett tid. Mange involverte har stått på og levert godt arbeid på korte frister, sier prosjektleder Kjell Arne Føinum i Celsa Armeringsstål AS.
“We finished the project on time. Many of those involved stepped up to the plate and delivered good work on short deadlines.”
These are words of project manager Kjell Arne Føinum at Celsa Armeringsstål AS.
Celsa Armeringsstål AS is building a hot charging system for the rolling mill. This will result in considerable energy recovery, no less than 30 GWh a year. By way of comparison, this is more than the production of the Vika and Svabo power plants – the two mini power plants linked to the waterworks at […]